Nigeria wins arbitration as Sunrise’s $400 million hydropower claim dismissed
What the source reports
Nigeria has won an international arbitration case after a tribunal dismissed a $400 million claim by Sunrise Power and Transmission over the long-delayed Mambilla hydroelectric project, Attorney-General Lateef Fagbemi said on Tuesday. The September 17 ruling removes a major legal obstacle to the 3,050-megawatt hydropower project, potentially reviving Nigeria’s biggest hydroelectric scheme after nearly two decades of delays.
Jumpstart your morning with the latest legal news delivered straight to your inbox from The Daily Docket newsletter. Sign up here. Fagbemi said the International Chamber of Commerce tribunal found that settlement agreements relied on by Sunrise were not binding on Nigeria because the officials who signed them lacked the authority to commit the government without presidential approval. He said the tribunal also found the agreements were tainted by corruption and contrary to Nigerian public policy, making them unenforceable. Fagbemi said Sunrise was ordered to pay…
TDBN presents the written preview supplied through the publisher's feed. Complete reporting, continuing updates, context, and corrections remain with the original report.
Read the complete report ↗